Makeni Ethanol Plant 

Summary

  • Construction of a new greenfield Bioethanol & Cogeneration Plant at Makeni for Addax Bioenergy
  • Country: SIERRA LEONE
  • Contract Period: 2011-2014
  • Basic Engineering: 6 months
  • Piping Design: 6 months
  • Supply of Equipment: 12 months

Basic Engineering

  • Process design for Juice Extraction, Purification and Evaporation
  • Management of equipment list
  • Specifications for purchase of equipment
  • Specifications for purchase of piping, valves and fittings

Plant Layout

  • Layout drawings for Juice Extraction, Purification and Evaporation
  • Layout drawings for Utilities
  • Structural Guide Drawings for equipment supporting steelwork and platforms
  • Updating of layout drawings with information from suppliers

P&ID’s

  • P&ID’s for Juice Extraction, Purification and Evaporation
  • P&ID’s for Utilities
  • Updating of P&ID’s with information from suppliers

Piping Design

  • 3D Plant model and pipe routing for the Juice Purification and Evaporation
  • Isometric drawings for all Juice Purification and Evaporation piping

Equipment Supply

  • 1 Heavy Duty Whole Stick Cane Shredder
  • 6 Juice Heaters
  • 5 Kestner Evaporators
  • 2 Robert Evaporators
  • 1 Juice Clarifier & 1 Flash Tank
  • 3 Condensate Receivers
  • 2 Condensers
  • 1 Syrup Cooler