ASH POST COMBUSTOR PROJECT

Summary

Erection of Magaldi plant and heat recovery plant for the Ash Post Combustor project at Union St Aubin.

  • Country : Mauritius
  • Contract Period : 2015

Engineering

  • Design of Steel supporting structure of Ecobelt conveyors
  • Design of hot air ducts from Air heater to Ecobelt conveyors
  • General layout and fabrication drawings of steel structures
  • Footprint drawing for civil works
  • General arrangement and fabrication drawings of walkways, staircases and operating platforms.

Procurement

  • Condensate Heater (Economiser)
  • ID fan
  • Ducting, LP steam and condensate pipes, valves and hanger supports
  • Structural Steel for fabrication of new steel supporting structures for Magaldi Equipments
  • Screwconveyors
  • Steam Coil Air Heater
  • Desuperheater
  • Condensate Receiver
  • Condensate pumps

Fabrication

  • Steelworks for Supporting structures

Mechanical Erection

  • Supporting structures of conveyors, platforms and walkway
  • Magaldi conveyors
  • Id fan/Screwconveyors/SCAH/Condensate Receiver/Condensate pumps
  • Ducting, LP steam and condensate pipes

Civil Works

Design, excavation and reinforced concrete works for the structural steel column pedestals to support conveyors