Summary
Erection of Magaldi plant and heat recovery plant for the Ash Post Combustor project at Union St Aubin.
- Country : Mauritius
- Contract Period : 2015
Engineering
- Design of Steel supporting structure of Ecobelt conveyors
- Design of hot air ducts from Air heater to Ecobelt conveyors
- General layout and fabrication drawings of steel structures
- Footprint drawing for civil works
- General arrangement and fabrication drawings of walkways, staircases and operating platforms.
Procurement
- Condensate Heater (Economiser)
- ID fan
- Ducting, LP steam and condensate pipes, valves and hanger supports
- Structural Steel for fabrication of new steel supporting structures for Magaldi Equipments
- Screwconveyors
- Steam Coil Air Heater
- Desuperheater
- Condensate Receiver
- Condensate pumps
Fabrication
- Steelworks for Supporting structures
Mechanical Erection
- Supporting structures of conveyors, platforms and walkway
- Magaldi conveyors
- Id fan/Screwconveyors/SCAH/Condensate Receiver/Condensate pumps
- Ducting, LP steam and condensate pipes
Civil Works
Design, excavation and reinforced concrete works for the structural steel column pedestals to support conveyors